Incorporated owners of One Beacon Hill v Match Power Investment Ltd
HK Court of First Instance, 25-Aug-2011
The defendant is the developer, owned by Cheung Kong (Holdings) Ltd. The IO is suing for HK$27m rectification costs for alleged defective work. The judge rejects the developer's attempt to strike out the action, which now proceeds to trial.
Various buyers of One Beacon Hill v subsidiary of Cheung Kong (0001)
HK Court of Final Appeal, 16-Jun-2011
Cheung Kong is refused leave to appeal by the CFA. Game over.
More buyers of One Beacon Hill v subsidiary of Cheung Kong (0001)
HK District Court, 15-Jun-2011
Cheung Kong sub hires overseas QC to continue case involving Beacon Hill buyers
HK Court of First Instance, 18-May-2011
Various buyers of One Beacon Hill v subsidiary of Cheung Kong (0001)
HK Court of Appeal, 21-Dec-2010
Various buyers of One Beacon Hill v subsidiary of Cheung Kong (0001)
HK Court of Appeal, 12-Nov-2010
Paragraphs 31-33 provide a damning criticism of the developer's behaviour in trying to trick purchasers out of their rights to claim for late completion of the property.
Various buyers of One Beacon Hill v subsidiary of Cheung Kong (0001)
HK Court of First Instance, 24-Dec-2009
Various buyers of One Beacon Hill v subsidiary of Cheung Kong (0001)
HK Court of First Instance, 16-May-2007